INSTALLATION

The turbine can be erected either on a concrete base (civil engineer to confirm and validate the design based on local conditions).

01
01

The preferred method of installing the turbine is a concrete foundation with steel reinforcement bars.

02
02

The foundation can be fabricated on-site using a contractor with experience in concrete/building industry.

03
03

Hydraulic erection system has been custom-designed for the turbine, using hydraulic rams with 50T capacity.

04
04

The tower is assembled in horizontal position, followed by assembly of the generator at the top end of the tower.

05
05

The struts and the blades are assembled at the ground level without help of any specialised tools. 

 

06
06

After assembly of all turbine parts on the ground level, the turbine is raised to its working position using dual hydraulic rams.

07
07

At the end of the whole process - the only missing component is the wind itself…